IMG_3253

Footings and Foundation Complete – Slab Next Step

  • July 28, 2015

The weather has been cooperating so progress continues to be made on the new facility. The footings and foundation work is complete and plumbing and electrical work is in progress under the slab. The building slab is scheduled to be poured later this week and into next week. The building itself is ready to be erected, so once the slab is poured, we should see vertical progress shortly thereafter. Continued good weather means progress – let’s keep it going!

Share This Page

Share on facebook
Facebook
Share on twitter
Twitter
Share on pinterest
Pinterest
Share on linkedin
LinkedIn

In Pictures